Ford (BlueOval Battery Park Michigan)

LFP battery manufacturing plant (initial scope 2,500 jobs; revised 2023). Initial battery-cell production began June 2026.

Investment
$3.50B
Permanent jobs announced
1,700
Status
Operational
Operations began
Jun 1, 2026
Why this project qualifies

With $3.5 billion in facility-specific investment and 1,700 permanent operating jobs announced, this project clears both of AFT's qualifying thresholds ($100 million in facility-specific investment OR 100 permanent operating jobs). This project also meets AFT's primary-source verification and physical U.S. manufacturing-footprint requirements.

View full methodology →
Why it matters

The battery manufacturing context.

Battery manufacturing has become one of the largest concentrations of new industrial investment in the United States. A network of cell plants is taking shape across the Midwest and Southeast, connecting automakers, battery producers, critical-material suppliers and energy-storage markets. Federal production incentives have accelerated that build-out, while the next test will be whether announced capacity converts into sustained domestic production.

Project record

At a glance

Company
Ford (BlueOval Battery Park Michigan)
Industry
Battery Manufacturing
Location
Marshall, Michigan
Investment
$3.50B
Permanent jobs announced
1,700
Status
Operational
Announced
Feb 13, 2023
Operations began
Jun 1, 2026
Added to tracker
Feb 19, 2026
Sources

Official references

  • Primary source
    https://www.michiganbusiness.org/press-releases/2023/02/marshall-ford-investment/
Related

Other projects to know

Back to the tracker/projects/ford-blueoval-battery-park-michigan-marshall

Follow America's industrial buildout

Get a free weekly email with new industrial projects and milestones worth tracking.

Get the weekly update