MP Materials 10X:
Building America's Magnet Supply
Rare-earth magnets help power electric motors and defense technology. MP Materials is building a new factory in Northlake, Texas, with a federal partnership designed to strengthen domestic supply. This report separates construction progress from planned capacity, financial support and production targets.[B][C]
By Dora C. Winters
MP Materials' Northlake campus is already included in AFT's manufacturing database. This report examines the same project and adds no investment or jobs to AFT's totals. See the Northlake project record.
Sources checked: October 10, 2026
Key facts
$1.25B+
Planned investment
MP’s announced investment for the Northlake campus.
Sources: [A] MP Materials, Northlake site-selection announcement, February 26, 2026; [F] Office of the Texas Governor, Northlake expansion announcement, February 26, 2026
1,500+
Direct jobs planned
Manufacturing and engineering positions at the site.
Source: [A] MP Materials, Northlake site-selection announcement, February 26, 2026
Under construction
Project status
MP confirmed construction progress in August 2026.
Source: [C] MP Materials, Second Quarter 2026 Results, August 6, 2026
2028
Commissioning target
Start-up and equipment testing; not full production.
Sources: [A] MP Materials, Northlake site-selection announcement, February 26, 2026; [D] MP Materials, 2025 Form 10-K, filed February 26, 2026
7,000 tons/year
Planned Northlake capacity
Metric tons of magnets annually after the plant scales.
Source: [E] MP Materials, First Quarter 2026 Form 10-Q
About $200M
State and local incentives
Grants and tax benefits spread over more than a decade.
Source: [A] MP Materials, Northlake site-selection announcement, February 26, 2026
Bottom line
Northlake has moved into construction, with commissioning targeted for 2028.[A][C] Its federal backing includes an agreement covering future magnet output.[B] The test ahead is whether MP can bring the factory into production and scale it to the planned capacity. Financial support and announced jobs do not establish that those outcomes have already been delivered.
What Northlake will make
The campus will produce neodymium-iron-boron magnets, commonly called NdFeB magnets. Denton County describes the facility as a manufacturing investment supporting advanced technology industries.[I]
MP's first-quarter 2026 filing sets out two distinct capacity targets: about 7,000 metric tons of magnets a year at Northlake, plus 3,000 at its separate Independence facility in Fort Worth. The combined target is 10,000 metric tons annually. These are planned capacities, not current Northlake output.[E]
The distinction is central to this report: the new Northlake factory and the existing Fort Worth operation are separate facilities.
What has been documented
- February 26, 2026: MP announced the selection of a 120-acre Northlake site.[A]
- April 2026: MP completed the land purchase for approximately $80 million, according to its first-quarter filing. This establishes an acquisition cost, not a total construction-spending figure.[E]
- August 6, 2026: MP reported that construction of 10X had accelerated. The same release separately discussed magnet qualification at Independence; that progress does not establish Northlake production.[C]
The sources reviewed do not establish a percentage of construction completed or a cumulative Northlake construction-spending total. AFT does not estimate either from the investment announcement.
What the Pentagon partnership covers
MP announced the partnership in July 2025. Its SEC filing describes several different forms of support:
- A $400 million preferred-stock investment in MP, plus a commitment for up to $350 million of additional preferred-stock funding.
- A ten-year price-protection agreement for neodymium-praseodymium products, using a $110-per-kilogram floor.
- A ten-year agreement covering 10X magnet production after commercial operations begin. Output can be directed to other customers with Pentagon consent.
- A contractual annual earnings floor for 10X of $140 million, adjusted for inflation, once it reaches the specified production milestone. This uses EBITDA, an earnings measure before interest, taxes, depreciation and amortization; it is not a construction grant.[B][D]
These arrangements support different parts of MP's business. They are not a single payment for the Northlake factory, and AFT does not add them together as facility investment.
Financing announcements need dates
The July 2025 announcement included a $1 billion bank financing commitment for developing 10X.[G] MP's later annual report says that commitment expired undrawn on August 26, 2025, following other fundraising and a revolving credit facility. It should not be presented as a current, drawn $1 billion construction loan. The same filing identifies a separate $150 million federal loan for samarium separation at Mountain Pass, California—not Northlake construction.[D]
This is why an announced financing package and money spent building a factory must be kept separate.
Texas and local support
Texas announced two grants: $12,880,500 from the Texas Enterprise Fund for campus corporate operations, and $53,457,500 from the Texas Semiconductor Innovation Fund for the manufacturing facility. Together, those announced grants total $66,338,000.[F]
MP described roughly $200 million in combined state and local incentives over more than a decade, including grants, abatements and exemptions.[A] Tax benefits over time are different from cash paid upfront. The public announcements reviewed do not establish that the whole incentive package has been disbursed. AFT has not reviewed all underlying incentive contracts or their payment schedules.
Future customers, future production
In July 2026, MP launched Project Swarm, allowing U.S. and allied drone and motor manufacturers to reserve future Northlake production capacity. The company expressly distinguishes those reservations from binding purchase commitments made today.[H]
MP's August release reported subscription agreements with multiple participants.[C] Those agreements signal customer interest, but they do not demonstrate magnets being shipped from Northlake.
What to watch next
- Construction milestones documented by MP or public records.
- Installation and commissioning of manufacturing equipment.
- The first confirmed commercial Northlake shipments.
- Progress toward planned annual capacity and operating employment.
- Incentive payments and any changes to the federal agreements.
Commissioning means bringing equipment and processes into service. A commissioning target alone does not specify when a factory will reach full output.
Frequently asked questions
Sources
- [A] MP Materials, Northlake site-selection announcement, February 26, 2026
- [B] MP Materials, Form 8-K, July 10, 2025
- [C] MP Materials, Second Quarter 2026 Results, August 6, 2026
- [D] MP Materials, 2025 Form 10-K, filed February 26, 2026
- [E] MP Materials, First Quarter 2026 Form 10-Q
- [F] Office of the Texas Governor, Northlake expansion announcement, February 26, 2026
- [G] MP Materials, Pentagon partnership announcement, July 10, 2025
- [H] MP Materials, Project Swarm announcement, July 30, 2026
- [I] Denton County, Northlake campus announcement, February 26, 2026