Mesabi Metallics has announced a $15 billion steelmaking complex planned for Lee County, Iowa. The company expects at least 1,750 permanent operating jobs once the plant is running. White House officials have said first steel production is targeted for 2030. Iowa and the company have signed a memorandum of understanding, and the governor has called an October 2 special legislative session to consider changes to the state's MEGA incentive program. The project is announced; the sources reviewed do not confirm that construction has begun.

By Dora C. Winters · Research as of September 29, 2026

Project Watch is separate from AFT's manufacturing database.

AnnouncedProposed integrated steel complex

Status summary

Bottom line

This is a major proposed industrial investment, but it is still a plan. The $15 billion and the expected jobs are announced figures, not money already spent or jobs already created. The sources reviewed do not confirm that construction has begun.

Related on AFTManufacturing recordView the tracked project →

This brief adds nothing to AFT's database totals.

What is being proposed, and where?

Mesabi Metallics has announced a $15 billion steelmaking complex planned for Lee County, in southeast Iowa. The company describes Essar Group as the project's sponsor.

According to the company, the plant would use a process called direct reduction. Iron ore pellets from the company's Minnesota mine would have oxygen removed without being melted. The still-hot iron would then go into electric arc furnaces, which melt it together with recycled scrap steel. The company says this uses less energy than a traditional blast furnace.

Only the county has been named in the sources reviewed. Those sources do not identify a city, street address or specific site.

What do the investment and jobs figures include?

The $15 billion is the announced investment for the Iowa steel complex. The company also describes a separate investment of roughly $3 billion in its Minnesota iron ore mine, bringing its combined program to about $18 billion. AFT counts only the Iowa figure here.

The company gives two job figures for Iowa:

Construction jobs are not counted as permanent jobs, and Minnesota mine jobs are not included in either figure.

What has been confirmed so far?

Confirmed: Mesabi Metallics announced the project on September 28, 2026. According to Governor Kim Reynolds' September 29 release, Iowa and the company have signed a memorandum of understanding, and the governor has called a special legislative session for October 2, 2026 to consider changes to the state's MEGA incentive program. The release does not publish the memorandum's terms.

Targeted, not guaranteed: White House officials have said first steel production is targeted for 2030, as reported by Reuters and The Gazette.

Not yet confirmed: The sources reviewed do not confirm that construction has begun, that financing is secured, or that state incentives have been approved.

What should readers watch next?

Several milestones will show whether the announced plan becomes a built plant.

AFT will update this brief as verified milestones are reached.

Frequently asked questions

Sources

Project Watch briefs are separate from AFT's manufacturing database and are not included in tracker totals, rankings or industry aggregates.