Intel Ohio One: What's Built, What's Delayed

Intel's Ohio One campus in New Albany was announced in 2022 as a two-fab chipmaking site. Construction is underway, but production targets have moved into the next decade[C]. This report sets out what has been documented, what remains a target, and how Ohio's and the federal government's agreements differ.

By Dora C. Winters

Intel Ohio One is included in AFT's manufacturing database. This Project Watch report examines that same project; it does not add another project or duplicate its investment and jobs in AFT's totals. AFT's tracked record for this project is Intel — New Albany, Ohio.

Sources checked: October 10, 2026

Key facts

More than $28B

Announced investment, two fabs

Intel's planned investment in the first two fabs, as stated on its Ohio page. A possible full buildout of up to $100B is a separate, longer-term idea.

Sources: [O] Intel, “Intel in Ohio”; [A] Intel, “Intel Announces Next US Site with Landmark Investment in Ohio,” January 21, 2022

3,000

Permanent Intel jobs planned

For the two-fab plan. Construction and indirect jobs are counted separately.

Source: [A] Intel, “Intel Announces Next US Site with Landmark Investment in Ohio,” January 21, 2022

$3.73B

Spent through 2024

Intel's report to Ohio. A further $3.2B was under signed contracts, for $6.9B spent or contractually committed in total.

Source: [D] Intel, 2024 Onshoring Annual Report and cover letter to the Ohio Department of Development, February 27, 2025

2030 target

First fab construction completion

Operations targeted for 2030–2031. These are targets, not guaranteed opening dates.

Source: [C] Intel, “Ohio One Construction Timeline Update,” February 28, 2025

$600M

Ohio onshoring grant

Fully received by Intel, according to its 2024 report. The agreement reviewed by AFT lists December 31, 2028 for investment, job and payroll obligations.

Sources: [D] Intel, 2024 Onshoring Annual Report and cover letter to the Ohio Department of Development, February 27, 2025; [E] Ohio Department of Development and Intel, Onshoring Incentive Grant Agreement, effective June 14, 2022

Amended

Federal funding agreement

Amended August 27, 2025. Some federal requirements remain.

Source: [H] Intel, Form 8-K on the Direct Funding Agreement amendment, August 2025

Bottom line

Intel has spent billions of dollars building two fab buildings and their support facilities in New Albany. By the end of 2024 it reported $3.73 billion spent and $6.9 billion spent or contractually committed in total[D]. Production has not started. Intel's targets are to finish building the first fab in 2030 and start operations in 2030–2031, with the second fab's construction completion targeted for 2031 and operations for 2032[C]. The Ohio grant agreement reviewed by AFT lists December 31, 2028 as the deadline for Intel's investment, jobs and payroll commitments. As of March 2026, no extension had been reported[E][L]. Separately, Intel and the U.S. Commerce Department amended Intel's federal Direct Funding Agreement in August 2025[H]. Ohio's grant agreement is a separate contract.

What Intel announced, and what it didn't

In January 2022, Intel announced an initial investment of more than $20 billion to build two leading-edge chip factories, known as fabs, in Licking County. It said the plan would create 3,000 Intel jobs and 7,000 construction jobs[A][N]. Intel also said the site could eventually expand to as much as $100 billion and up to eight fabs over the decade[A]. That possible full buildout is separate from the announced two-fab plan. AFT does not count the possible $100 billion expansion as committed investment.

Intel's Ohio page now describes more than $28 billion in planned investment for the two fabs[O]. Ohio's grant agreement sets a lower floor: at least $20 billion in fixed-asset investment[E].

The job figures cover different scopes:

What has been built

These records describe completed tasks. They do not provide a basis for calculating percentage completion.

Building done vs. production started

Intel's schedule separates finishing a building from starting production.

Before production starts, a completed fab still needs manufacturing tools installed and qualified. Intel describes these dates as targets tied to market demand[C][I]. In its quarterly report for the period ended June 27, 2026, Intel described the Ohio manufacturing facility as a long-term investment and gave no revised opening date in that passage[M].

The money: spent, signed contracts and announced investment

Spending and signed contracts measure financial commitments toward the project. They do not indicate how complete the project is.

Ohio's grant agreement

The Ohio Department of Development's $600 million onshoring grant agreement with Intel has an effective date of June 14, 2022[E].

On jobs: Intel reported 163 employees as of December 31, 2024, and 127 full-time equivalents during 2024[D]. Those figures describe staffing during construction. AFT has not confirmed how the agreement counts qualifying jobs, so it does not compare them with the 3,000-job commitment.

The federal agreement, a separate contract

In November 2024, the Commerce Department finalized up to $7.865 billion in direct CHIPS funding for Intel across four states, including up to $1.5 billion for the Ohio project[G][F].

On August 27, 2025, Intel and the department signed an amendment to that Direct Funding Agreement, alongside issuing shares of Intel stock to the government[H]. Intel's filing says the amendment:

Intel received $5.695 billion under the amended agreement[H]. Other federal requirements remain, including:

These changes concern Intel's federal Direct Funding Agreement. Ohio's grant agreement is a separate contract.

What to watch next